Waynesboro Park & Ride Expands

An expansion of the Town Center Park and Ride commuter lot in Waynesboro began construction the end of March and is scheduled to be complete in May of 2022.

The $1 million project will increase parking capacity from 120 to about 175 spaces, install a bus stop with a covered shelter, and will repave and improve on-location lighting. Additional amenities include bicycle racks, sidewalks, landscaping and infrastructure to accommodate future charging stations for electric vehicles.

The commuter lot, located near the Interstate 64 exit 94 interchange at Route 340 (P. Buckley Moss Drive), will remain open during construction. Barricades will separate the work zone from areas open to the public. The project is funded by the SMART SCALE transportation prioritization program. Additional information can be found on the Virginia Department of Transportation project page.

Posted in News.